City Council on Ice Rink
Approval to Redesign to Reduce Construction Costs
June 2, 2008
Item 5B3 on the City Council Agenda for June 2, 2008
Streaming
video of meeting
Once it starts playing you
can go directly to the ice rink item by choosing "5.B.(3) AUTHORIZATION
TO EXECUTE AN AMENDED..." from the list underneath the picture.
Staff Report
- Asked the Council to approve another $406,000 for the
architect to redesign the proposed building to try to save money on
construction.
- Additional expenditures will be made to rebid the contract
and otherwise pay for city staff time, adding up to about a half
million.
- They are hoping to save $1.1 million or more on the
construction cost.
- The expected savings are via unspecified "structural
foundation revisions" and making the exterior of the building of mostly
"block wall construction", resulting in "reduction of expansion joint
requirements and drywall finishes". (I.e. think of the
fortress walls
of Bed Bath & Beyond, Petsmart, etc, but the entire 450 feet of the
ice rink wall would be on one
vertical plane.)
- The redesign is expected to provide about 5000 additional
square feet for spectator seating. No mention of how many seats
that equates to.
- The resulting building is expected to be less energy
efficient then the current design but otherwise the interior
functionality is expected to be equivalent. The exterior will be
less aesthetic but may cost less to maintain.
- Now expect construction to start by spring 2009 and take
about 16 months.
- Mentions expecting to resolve construction access and
"other agreement-related" issues between the city, Edison, and PCC by
the end November.
Finance Committee Meeting
The item was heard first by the Council's Finance
Committee at 3 pm. But this meeting was a joint meeting with the
full
Council because they were also discussing the City's Operating Budget
for 2008. The only Council members absent from the committee
meeting
were Gordo and Madison. The item took about 15 minutes.
- Public Works director Martin Pastoucha summarized.
- Said expected $800,000 or more net savings.
- Only "area of play" is structural system
- "Side benefit" is additional seating on balcony.
- Redesign is to be completed through summer.
- He offered to show the "design elements", but no one took
up the offer so no drawings were shown.
- Councilman Tyler had some questions.
- Tyler asked about financing. Pastoucha said they
are working on it.
- Tyler asked about "construction cost benchmark".
Pastoucha said not applicable because of the unique issues with the
site, but the benchmark is around 250 to 285 per square foot.
This
project is only in that ballpark if the $4.5 million footprint cost is
not included. (He did not go into any detail, but what he was
probably
referring to is the difficulty in accessing utilities, ground stability
issues that require the use of piles, possibly the extra cost for
construction access.)
- Tyler asked if the architect had done ice rinks
before. Answer was yes, example given was Valencia ice center.
- Tyler asked about the reference to reduction in energy
efficiency. Answer included a few details about
problems with air stratification and avoiding condensation.
Mentioned block walls absorb moisture so additional work is needed to
avoid sweating. There was more indirect daylight in former design
which reduced need for indoor lighting and resulting heat
generation.
Council indicated they didn't want so many details.
- Tyler asked if building would still be able to meet LEED
certification requirements. Answer was that it could be difficult
but
staff was not yet asking for an exception to the city's requirement
that all city building projects meet LEED requirements.
Said they are
still looking into ways to insulate the block walls.
- Staff was asked about the mentioned unresolved
problems with PCC and Edison.
- Answer was that it is the construction access.
- The existing agreement with PCC is just verbal
and hasn't been taken to Council yet. It does not allow
construction
access via the PCC parking lot. Edison has given permission to go
through the east side of the park. So that is the plan that was
included in the defunct construction bid process last winter. PCC
was
"adamant" about not allowing construction access due to too much
potential conflict with students. But city staff plans to
re-approach
them on that.
- Haderlein asked how a stronger case can be made to
PCC.
- Acting City Manager Melekian indicated they
would be coming back to Council regarding the financing. The PCC
route
would be better from a cost standpoint.
- Pastoucha was asked isn't it necessary for the route to
be decided before it is put out for bids again. Answer was yes,
it
should be.
- Haderlein asked for an update on the PCC matter in two
months. Tyler indicated it could come via a "green sheet".
(That is a
way the staff uses to distribute information to all the Council members
without it being on a public meeting agenda.)
- The finance committee approved increasing the architect's
contract to do the redesign.
More Information
Afterwards, our association president met with Segun, the
city's planner for the project and got more information.
- City staff had looked at projections for three possible
alternate designs and the block wall construction was the most feasible.
- The proposed concrete block wall construction is much
heavier then the previous steel column design, but the weight is spread
out more. The structure will still need pilings but instead of
them
all being 40 feet deep, some inner ones will only need to be 30 feet
deep.
- The roof connections are much simpler for concrete block
design.
- Concrete is expensive, but steel prices have really been
soaring. It is the saving on the amount of steel that really
makes the
difference.
- The "extra" seating space comes from moving the east wall
back out above the locker rooms instead of having a balcony. In
other
words, returning to the original configuration before they moved the
wall in to save money on the roof and air conditioning costs.
Expected to result in a potential seating capacity of about 500 again.
- No built in bleachers/seats are planned on the
"balcony". That'll be up to the operator.
- Colors/patterns of block walls are part of what is to be
determined during redesign. Expects the exterior of the blocks to
be
rough, probably painted. Translucent blocks are still
expected in
"random" pattern in the lower east wall to allow light into the locker
rooms / offices.
- Electricity to come to site either down the center of the
park (under the lot) or around the park on the west side. PWP to
determine which is best later.
- Water and sewer are to come from/to our neighborhood,
probably via upgraded pipes on Alameda.
- Still plan to have a reservoir for ice melt which can be
used for landscape watering, including a connection that the park could
link to at some future time.
- No mention of solar arrays now; none were in plan before.
- Preliminary drawing shows some large windows which extend
off the top of
the east wall. These windows would allow light in, but not
visibility. Same drawing also still shows green screen frameworks
that
plants would supposedly grow up on from base of building. There
is
also still the shadow box sign and wierd parapet, although it looks
like different materials.
- Probably no trees on east side because of Edison
wires.
(However, if the park can have trees so near the wires, why not the
rink project?)
- Segun said landscaping is still in the budget but agreed
that might suffer as an easy target for cutting as a "do later" that
may never happen. But he agreed that staff should not cut it on
its
own; should force Council to make any such decision and promises.
Council Meeting
- There were a number of ice rink supporters who spoke about
how much it is needed and how they need at least 500 seats to have the
events they think they should have, and how they need a commitment that
the current rink won't close before the new facility is open.
Also
mentioned that important to have it open before the 2010 winter
olympics because of the interest that will generate.
- Madison and Gordo both made very gung-ho statements about
getting it done ASAP and supporting the speaker's statements about
having enough seating and not skimping on functionality.
- No one said anything about the stated purpose/goal of the
rink not being to host large events and that isn't where the revenue is
expected to come from. And the approved
environmental
documents specify 2 to 4 large events per year.
Next steps
- Revised design expected to go to Design Commission in
August time frame.
- City staff may hold a community meeting prior to that.
- City staff should be bringing financing revisions/options
to Council sometime during the summer.