Ice Rink Conditional Use Permit (CUP)
A Conditional Use
Permit (CUP) is
required because it will be commercial recreation on land zoned as Open
Space.
The request for
a CUP was heard by Hearing Officer Paul Novak on
July 5, 2006.
This is the notice of the hearing which was posted on utility poles on
Avocado Ave and sent to homeowners within 500 feet of the project
site. Hearing
Notice
Zoning staff prepares a report for the hearing officer which
summarizes the project plan, explains how the project meets the
necessary "findings" that the proposed usage is consistent with the
zoning requirements, and recommends conditions (requirements) for the
permit. If the developer or user later violates the specified
conditions, the usage permit could be revoked.
Staff report to
the Hearing Officer
(pdf, 560 kb)
The public is able to speak at the hearing. Several area
residents requested additional conditions on the permit, most of which
were granted. A request was also made to make the closing time 10
pm instead of midnight. That request was denied.
CUP #4646 was
granted under the conditions listed
in the Staff Report plus some additional
conditions.
Conditions approved from the
staff report (Attachment B) are:
The applicant or successor in interest shall meet the following
conditions:
- The site
plan, floor plan, elevations, and building sections submitted for
building permits shall substantially conform to plans submitted and
stamped "Received at Hearing, July 5, 2006", except as modified herein.
- The
proposed project, Activity Number PLN2005-00617, is subject to the
City's Condition/Mitigation Monitoring Program. Condition Monitoring is
required for your project. Under the Monitoring Program, your project
will be inspected by Code Compliance staff to determine compliance with
the conditions of approval. The Condition/Mitigation Monitoring
inspection will occur during the term of the project. Required
monitoring fees for inspections shall be paid on or after the effective
date of this permit, but prior to the issuance of any building permits.
Contact the Code Compliance Staff at (626) 744-4633 to verify the fee-
All fees are to be paid to the cashier at the Permit Center located at
175 N. Garfield Avenue. The cashier will ask for the activity number
provided above. Failure to pay the required monitoring fees prior to
initiating your approved land use entitlement may result in revocation
proceedings of this entitlement.
- The
applicant, or successor in interest, shall comply with the Mitigation
Monitoring Reporting Program as outlined in Attachment E to this report.
- The hours
of operation of the facility shall be limited to 6 a.m. to 12 a.m.,
seven days a week. Any additional hours of operation shall require the
modification of this Conditional Use Permit.
- The
applicant shall submit Master Sign Plan application for all signage on
the site.
- Design
Review is required for this project prior to the issuance of any
building permits.
- Because
this is a City project on Open Space zoned property, the project shall
comply with the public art design standards of Section 17.40.100 of the
Zoning Code.
- Use of the
Southern California Edison property to the immediate east for access to
the ice rink facility's parking lot shall require the submittal of a
lease agreement or similar document to the Zoning Administrator prior
to the issuance of any building or grading permits.
- Use of the
Southern California Edison property to the immediate east for ice rink
facility patron parking shall require the modification of the
Conditional Use Permit.
- Prior to
the issuance of any building permits, the City and project operator
shall seek additional parking options and submit parking management and
traffic control plans for major events such as a sold out performance
and a hockey tournament, events that are anticipated to occur once or
twice a year on weekends.
- The Zoning
Administrator, at any time, can call for a review of the approved
conditions at a duly noticed public hearing. These conditions may be
modified or new conditions added.
- The
applicant, or successor in interest, shall meet the applicable code
requirements of the Zoning Code and of all other City Departments at
all times.
Additional
conditions added during the hearing based on resident and
applicant
(city) input are:
- Use of the
PCC property for access to the site shall require
the submittal of a lease agreement or similar document to the Zoning
Administrator prior to the issuance of any building or grading permits.
- Construction
access shall be prohibited through the residential community east of
Avocado as a component of the Construction Staging and Management Plan
to the satisfaction of the Zoning Administrator.
- The
traffic signal at the project driveway shall be operational prior to
issuance of a Certificate of Occupancy.
- A
pedestrian path from the residential community on the east to the park
shall be maintained for the duration of the project.
- All night
lighting shall be shielded and directed on-site.
Additional Bits of Information
gathered at the CUP hearing:
- City staff
is intending to design and construct the signal and street improvements
at the driveway entrance on Foothill as part of the Capital Improvement
project that will cut Kinneloa through to Titley and Walnut through
from Sunnyslope to Kinneloa. There is intent to use one signal
controller for the driveway and Titley because they are so close
together (though still 150 feet apart). City staff did not
want to commit to having the signal in place by the time the ice rink
opens because the capital improvement project has not yet been designed
and the funding is not complete. The hearing officer told them he
thought there was enough time to get that done and put in a condition
requiring it be done before the ice rink opens.
- A person
attending from the current ice rink operators said that adults, and
adult accompanied children, are welcome to come into the facility and
watch the skating anytime for free, except on the rare occasions of
special events.
- An
additional modification to the parking plans was under
consideration in July 2006. That would put a row of parking to
the west of the
access road, facing the east side of the building. Because the
building entrance is in the middle of the east side of the building,
these spaces would be the most frequently used and the parking lot
would only be needed during busier times. From a practical usage
standpoint, this makes a lot of sense. In order to make such a
change, more space would need to be leased from Edison and the
Conditional Use Permit would need to be modified.
- The
developer (city) representative stated during a discussion of potential
screening of residential areas from the parking lot and access road
that they "plan to provide shrubbery screen on Avocado". It
was also stated that it would not be practical to put a wall on the
west side of the parking lot due to the slope of the land and that
putting in the foundation for a wall would damage the existing
trees. Landscape screening is doable.